February 26, 2018
401-348-2562
The construction/replacement of the Downtown Culvert is moving ahead and is scheduled to be completed by the end of May, 2018. The first phase of the replacement of the culvert is complete and the traffic pattern has been reconfigured for the next phase. The contactor is D’Ambra Construction, Inc. with construction oversight being done by CDR Maguire. This project is funded with CDBG Disaster Relief funding
September 19, 2017
Construction operations are scheduled to begin in early to mid-October of this year and are anticipated to be completed by the end of May of next year. NGrid gas must complete a gas main replacement project before construction can commence. Gas main work will take place over the next few weeks. Culvert replacement work will be divided into 4 segments each of which will require modified traffic patterns and some loss of parking.
The contractor for this work is D’Ambra Construction, Inc.
Construction will occur typically from Monday through Friday, 7 AM to 4 PM
Construction operations include:
• Utility relocation
• Culvert replacement
• Sporadic curbing removal and resetting, concrete work – Wheel Chair ramps and islands
• Crosswalk Replacement
• Roadway Replacement and re-striping
We are aware of the inconvenience caused by our activity and apologize in advance. Rest assured that we will do everything possible to minimize the impact of the construction to you. If there are any questions regarding construction work, please contact the Project Manager, James Caroselli of CDR/Maguire Engineering at 401-258-2519.
Thank you in advance for your understanding and cooperation