Preliminary Downtown Paving Schedule as of 9/17/18
Week of September 16th
Union Street, Broad Street (from Elm St. to High St.) High Street (from Broad St. to Grove Av.) and Canal Street (from High St. to Railroad Av.)
Cold Plane work to be done at night on 9/18 & 9/19, weather permitting. Prep for paving, protect crosswalks, apply tack coat and pave on 9/19, 9/20 and 9/21.
Striping will be done twice; temporary paint immediately after paving and Epoxy striping 2 weeks after paving.